Steel Pipe Schedule Chart: SCH 10, 40, 80, 160 Explained

Oct 21, 2026

Leave a message

A pipe schedule is a wall thickness series, not a pressure rating. The same schedule number produces different wall thicknesses at different sizes, and SCH 40 stops being identical to STD above NPS 10 - which is where most ordering errors begin.

This chart covers NPS 1/2" through 24" for the four schedules that account for most carbon steel pipe orders, with wall thickness and theoretical weight per metre so quantities can be checked before the container is loaded.

What The Schedule Number Actually Means

The system dates from the 1920s, when the American Standards Association needed a way to standardise wall thickness as pipe sizes grew. The original formula was simple: schedule number equaled 1,000 divided by the allowable working pressure at that size. A pipe that had to carry 100 psi got schedule 10; one rated for 25 psi got schedule 40.

The formula is no longer used. What survived is a fixed table of wall thicknesses, where the same schedule number represents progressively heavier wall as the diameter increases. This is why SCH 40 at 2" is 3.91 mm and SCH 40 at 24" is 17.48 mm - the number stayed the same while the wall grew with the pipe.

Two consequences follow directly from this, and both cause specification errors:

  • The schedule number does not indicate pressure capability on its own. A 2" SCH 40 pipe and a 24" SCH 40 pipe are both "SCH 40" and have vastly different pressure ratings.
  • Schedule and "STD / XS" are different systems that overlap only below 10". Details below the chart.

The Schedule Chart: NPS 1/2" to 24"

Wall thickness in millimetres, theoretical weight in kg per metre. Weight is calculated as (OD − t) × t × 0.02466, the standard formula for carbon steel pipe, and excludes end finish or coating.

NPSOD
mm
Wall thickness (mm) Weight (kg/m)
SCH 10SCH 40SCH 80SCH 160 SCH 10SCH 40SCH 80SCH 160
1/2"21.32.772.773.734.781.31.31.61.9
3/4"26.72.872.873.915.561.71.72.22.9
1"33.42.773.384.556.352.12.53.24.2
1-1/4"42.22.773.564.856.352.73.44.55.6
1-1/2"48.32.773.685.087.143.14.05.47.2
2"60.32.773.915.548.743.95.47.511.1
2-1/2"73.03.055.167.019.535.38.611.414.9
3"88.93.055.497.6211.136.511.315.321.3
4"114.33.056.028.5613.498.416.122.333.5
6"168.33.407.1110.9718.2613.828.342.667.6
8"219.13.768.1812.7023.0120.042.564.6111.3
10"273.04.199.2715.0928.5827.860.396.0172.3
12"323.84.5710.3117.4833.3236.079.7132.0238.7
14"355.66.3511.1319.0535.7154.794.5158.1281.7
16"406.46.3512.7021.4440.4962.6123.3203.5365.4
18"457.06.3514.2723.8345.2470.6155.8254.6459.4
20"508.06.3515.0926.1950.0178.6183.4311.2564.8
24"610.06.3517.4830.9659.5494.5255.4442.1808.2

Values per ASME B36.10M. Wall thickness is nominal; mill tolerance is typically −12.5% on seamless and −10% on welded pipe, so minimum wall at the low end of tolerance is measurably below the nominal figure.

Where SCH 40 Stops Being STD

STD, XS and XXS are the older three-tier designation, and they map onto schedules only at small sizes. This is the single most common source of mismatch between a purchase order and a mill certificate:

SizeSTD equalsXS equals
NPS 1/8" – 10"SCH 40SCH 80
NPS 12" and above9.53 mm wall, not SCH 4012.70 mm wall, not SCH 80

At 12", STD is 9.53 mm while SCH 40 is 10.31 mm - close enough to be confused, different enough to fail a weld procedure or a weight check. Above 12" the gap widens: 24" STD is 9.53 mm against 17.48 mm for SCH 40.

If a drawing says "SCH 40" and a mill certificate says "STD", they are not the same product above 10". Ask for the wall thickness in millimetres, not the designation.

Choosing A Schedule In Practice

Four factors decide it, and the design calculation only covers the first:

  • Design pressure and temperature. ASME B31.3 gives allowable stress by material and temperature; wall thickness follows from the hoop stress equation with corrosion allowance added. Schedule is the output, not the input.
  • Corrosion allowance. Water and chemical service often adds 1.5–3 mm. That allowance is frequently met by stepping up one schedule rather than ordering a special wall.
  • Threading and welding. SCH 10 at small sizes is thin enough that threading removes most of the wall at the thread root. NPT joints generally want SCH 40 minimum from 1" down.
  • Support and handling. Thin-wall large-diameter pipe (SCH 10 at 24" is 6.35 mm on a 610 mm OD) dents easily and needs wider support spacing than the span tables assume.

Cost Impact Of Stepping Up A Schedule

Weight scales roughly linearly with wall, so schedule changes translate almost directly into cost. From 6" SCH 40 to SCH 80 adds 51% to the weight per metre; from SCH 40 to SCH 160 at the same size it more than doubles. On a 1,000-metre order that is the difference between roughly 28 and 68 tonnes.

This is why the schedule decision belongs at design stage. Re-rating a line after the order is placed usually means either re-ordering pipe or accepting a lower pressure rating than the process needs.

Frequently Asked Questions

Is SCH 40 the same as schedule 40?

Yes - "SCH 40" and "schedule 40" are the same designation. The abbreviation is a formatting convention, not a different series.

What is the wall thickness of 6" SCH 40 pipe?

7.11 mm nominal, on a 168.3 mm outside diameter, giving a theoretical weight of 28.3 kg/m. Minimum wall at −12.5% tolerance is approximately 6.22 mm.

Why is SCH 80 heavier than SCH 40 by more than expected?

Because the schedule series is not linear. Between SCH 40 and SCH 80 at 8", wall goes from 8.18 mm to 12.70 mm - a 55% increase in wall and in weight. Small sizes show smaller steps; large sizes show larger ones.

Does a higher schedule always mean higher pressure rating?

For the same size and material, yes. Across different sizes, no - a 2" SCH 80 pipe and a 16" SCH 40 pipe are not comparable, because pressure rating depends on the wall-to-diameter ratio, not the schedule number alone.

Which schedule is used for API 5L line pipe?

API 5L specifies wall thickness directly in millimetres or inches rather than by schedule, because line pipe is designed to a pressure class. Schedules still appear on water, steam and process piping ordered to ASME B36.10M.

Ordering Carbon Steel Pipe To A Schedule

We supply ASTM A53 carbon steel pipe and A106 seamless pipe from SCH 10 to SCH 160, in sizes from 1/2" to 24", with mill test certificates to EN 10204 3.1. Tell us the size, schedule, grade and quantity and we will confirm wall tolerance, length and delivery in one reply.

For the full range of pipe types we produce, see carbon steel pipe. If you are deciding between grades rather than schedules, the SCH 40 ordering case in our SCH 40 wall thickness guide shows how a schedule mismatch typically surfaces at the drawing review stage.

Send your pipe schedule and quantity for a quotation - we reply within one working day with price, weight and loading plan.

Send Inquiry
Have a Question? Get in Touch.

Whether you need product information, technical support, or a steel supply quotation, our team is ready to assist you.
Contact us by phone, email, or the inquiry form, and we will get back to you as soon as possible.

Contact now!